In H2 2016 PJSC “Dunaysudoremont” had repaired the following vessels:
M/V “Aleksandr” (Shipchart Llc)
The ship repair was carried out throughout August 15th 2016- October 10th 2016. We have replaced over 160 million tons of metal.
PTC “DonRechFlot” vessels
Throughout August- October 2016 our plant has successfully accomplished maintenance and renovation of several vessels (m/v “Volga-Don 211”, “m/v “Volga-Don 213” and m/v “Sibiskiy -2116”).
“DDSG-Makhart” vessels
We have conducted dockside repair of m/v “Poltava” and m/v “Miscolt” in the beginning of November 2016. These vessels are owned by “DDSG-Mahart”- the largest Danube logistic company.
PJSC “Ukrainian Danube Shipping Company” vessels
In Q4 we have carried out maintenance of m/v “Russe” and m/v “Dmitri Kalinin”, so as dock inspection for m/v “Dnepr”.
M/v “Ocean Force”
M/v “Ocean Force” had required cleaning and painting, which were carried out in dock N 4 in the shortest time possible.
d/v Tiligulsky (branch of Delta-Pilot, State Enterprise “Ukrainian Sea Port Authority”)
According to the planned schedule, d/v “Tiligulsky” has been put in dock since November to complete dry dock works.